Lots of visual progress has been made on Cincinnati’s $120 million Smale Riverfront Park over the past few months.
Since the last construction update in June, project manager Dave Prather explains that the steel framing for Carol Ann’s Carousel is now taking shape, and that the Vine Street fountains and steps have now fully taken on their form. These steps and cascading fountains will be similar to the Walnut Street fountains and steps already completed to the east.
Prather also takes us inside the rentable event space beneath the carousel and fountain plaza.
While it is still quite messy with construction activity, Cincinnati Parks officials are actively promoting it and booking reservations now. Park officials tell UrbanCincy that the Anderson Pavilion will have two event spaces – Longworth Room and Mendenhall Room – that can accommodate up to 300 people. Special events can be booked through Premier Park Events at 513-221-2610.
During the nearly 12-minute video, you can also now see a new view of the Ohio River now that excavation has begun on the park’s great lawn. This area of the park will bring visitors as closer to the water than anywhere else.
Most all of the work profiled in this latest video update is anticipated to be complete in time for the 2015 MLB All-Star Game at Great American Ball Park. The week-long festivities leading up to the weekend of games is expected to being thousands of visitors and millions of eyeballs to the city’s central riverfront.