Hamilton County Pushes Forward With Latest Phase of The Banks

Hamilton County has awarded the latest bid package for a variety of trade contracts on the infrastructure work for Phase III of The Banks, which includes a 690-space addition to the Central Riverfront Garage and a one-block addition of other infrastructure south of Freedom Way.

All three contacts were valued at a combined $653,228; and all went to area companies. According to Phil Beck, project executive for The Banks development, Universal Contracting Corporation will perform site work, Geograph Industries will handle signage, and ESI will manage security of the site.

While not particularly large or sexy contracts, project officials say they are representative of the continued progress being made at the massive central riverfront mixed-use development.

“Awarding these contracts for work at The Banks signals that another aspect of the riverfront development is nearing completion,” said Chris Monzel (R), president of the Hamilton County Board of Commissioners. “This phase of the project sets the stage for more economic impact.”

The University of Cincinnati Economics Center has estimated that, once fully completed, the first phase of The Banks will positively impacting the local economy by some $276 million per year – a figure they expect to grow substantially once later phases are built out. General Electric’s new 338,000-square-foot Global Operations Center, alone, is projected to boost the region’s economy by roughly $1 billion annually.

While Hamilton County is overseeing the construction of the infrastructure work at Phase III, the City of Cincinnati and the private development team is making progress on the vertical build of GE’s new building, the 165-room AC Hotel, and 291 apartments and 19,000 square feet of retail within the first two phases of the project.

THP Limited and Burgess & Niple are in charge of the design of Phase III work, while Messer is handling the construction.

As of now, all the infrastructure work being managed by Hamilton County and the City of Cincinnati is $29.3 million within budget; and project officials say that they have achieved 30% Small Business Enterprises participation on all work, but just 17.3% on phase three activities thus far. Beck also says that phase three work is on schedule to be complete by September.

Categories
Business Development News

Project Officials To Move Forward With Phase III of The Banks Ahead of Schedule

Business leaders and public officials from the City of Cincinnati and Hamilton County will gather tomorrow morning to celebrate the groundbreaking of the next phase of work at The Banks.

As has been done in the past at the massive central riverfront development, the first work to be done will be the construction of a public parking garage that will lift the project out of the Ohio River’s flood plain. From there, the existing public streets surrounding the project site will be extended to frame the block.

While the event is being touted as a groundbreaking ceremony, workers from Prus Construction and Beaty Construction began mobilizing on the site to perform preparation work. The news is a bit of a departure from previous announcements that said construction work would hold off until the close of the Bengals season in order to preserve parking for tailgaters at Paul Brown Stadium.

In this particular phase of work, project officials say that 690 parking spaces will be built on two levels that will be connected with the rest of the underground parking deck at The Banks, which has been casually described as one of the largest underground parking structures in North America.

This $29.3 million effort is being jointly funded by the City of Cincinnati, Hamilton County, and the State of Ohio’s Jobs Ohio program. Representatives from the various public agencies funding the project say that it will create an estimated 200 jobs, with at least 30% of the contract totals spent with Small Business Enterprises.

Such a claim for small business inclusion is on-target for what the project has been delivering thus far. As of June 2015, the latest reporting date, The Banks has had an average of 36% small business participation and approximately 17.5% minority and female workforce participation.

Nearby work continues on the private sector vertical construction of Radius, a 291-unit apartment midrise with 19,000 square feet of street-level retail, and the 340,000-square-foot General Electric Global Operations Center.

Once these two phases of work are complete, it will allow for the next phase of Smale Riverfront Park to move forward, and will set the stage for private real estate development south of Freedom Way and in between Race and Vine Streets.

So far, Carter USA and the Dawson Company have yet to reveal what will ultimately be built on top of this latest garage extension, but most suspect it will be some combination of apartments and condominiums.

While The Banks has received much positive praise as of late, it has not come without its struggles. The retail in the first phase of the project continues to find its footing, and the area continues to struggle with a brand identity and architectural designs that people feel are worthy for the prominent piece real estate that this development occupies.

Categories
Development News

Project Officials Ready to Move Forward With Next Phase of The Banks

Officials overseeing the development of The Banks have announced that they will soon proceed with the design and construction of the infrastructure needed for the next phase of the massive riverfront project.

Yesterday, at a special meeting of The Banks Steering Committee, the eight-member group unanimously voted in favor of moving forward with what they expect to be $29.3 million worth of work, which would then provide the platform for millions more in private investment in the form of offices, residences and retail on what is referred to as Lot 24.

As has been the case with all prior phases of the mixed-use development, the City of Cincinnati and Hamilton County will build out the utilities and roadway network, and construct a 690-space, two-level parking garage that will lift the site out of the Ohio River floodplain. Carter and The Dawson Company – the private development team selected for the project – would consider what elements should be included and then proceed with building and leasing out whatever is built on top of the parking decks.

A guiding principle that has not changed since the beginning of the development process is that the underground parking garage will be reserved for public parking, leaving Carter-Dawson to develop additional above-ground parking to satisfy the City’s mandatory parking requirements.

The Steering Committee said that the public work will be funded through the issuance of $22 million in tax increment finance bonds, and $7 million from the State of Ohio. Project officials say issuance of the bonds is expected to come within the coming months.

While the Carter-Dawson team has not yet decided the exact mix for this third phase of work, it is widely expected to be primarily residential. In total, the zoning and infrastructure for the site will allow for around 320,000 to 400,000 square feet of developable space.

The timing of the announcement could not be better, with work rapidly progressing on General Electric’s 338,000-square-foot Global Operations Center, 19,000 square feet of retail space, and the 291 apartments at the phase two site to the immediate north; and with the announcement that AC Hotels will develop the long-sought hotel along Main Street in front of Great American Ball Park.

Phase two work is expected to be completed in phases throughout 2016, while AC Hotel by Marriott is expected to open in spring 2017.

While management with the Cincinnati Bengals expressed some concern over the loss of one of the team’s few remaining tailgating lots, The Banks itself is evolving into more of an entertainment district than many had thought.

In April, state officials approved a new open-container district law that will soon be in place at The Banks; and yesterday, in a separate move, the Cincinnati Reds applied for a zoning variance to allow for the installation of a video board that will overlook Freedom Way – providing live video programming when the surrounding streets are shut down to cars for special events. Such moves could render tailgating lots obsolete as fans move to the streets on game days.

Project officials say the phasing of construction at the 18-acre site has been carefully coordinated between the district’s various stakeholders, along with the construction schedule of Smale Riverfront Park. As park work has moved west so has work at The Banks, and with the latest work on the park taking place just south of phase three of The Banks, the timing makes perfect sense.

If all goes according to plan, this next phase of infrastructure work could begin as soon as January or February – just after the conclusion of the Bengals football season.

Categories
Business Development News

Townhomes Removed from Development Plan for The Banks

Hamilton County leaders announced last Thursday that they had struck a deal with the Cincinnati Bengals regarding a number of issues pertaining to the county’s stadium contract with the team.

The biggest component of that new agreement is that the Bengals will waive their veto right over the heights of buildings at The Banks. This clause in the stadium deal, signed in 1997, delayed the start of construction of Phase IIA work at The Banks by more than a year, and posed a significant risk to the City of Cincinnati in its efforts to lure General Electric and its new Global Operations Center to the central riverfront.

Now that the agreement is signed, developers of The Banks have announced that they will immediately begin construction on Phase IIA project that will include 291 apartments and 19,000 square feet of retail space.

Should the city succeed in its efforts to land General Electric’s facility at The Banks, it is expected that its new office tower would either be located at the office pad within the Phase I footprint, or more likely on top of the street-level retail adjacent to the apartment midrise at Phase IIA.

The development team believes both sites could accommodate the approximately 400,000 square feet of office space desired by General Electric.

The announcement also brought with it renewed questions about the status of the hotel at Phase I, located immediately across the street from Great American Ball Park. On that note, the developers said that they are still working to sign a hotel operator for the space, and that it is unlikely it will be completed ahead of the 2015 MLB All-Star Game.

That leaves only one element of Phase I of The Banks still in question – the oft-forgotten townhomes lining the Schmidlapp Event Lawn.

When asked about the status of the townhomes, and if their delay in moving forward was related to constructability issues with the adjacent and unbuilt hotel site, Libby Korosec, spokeswoman for The Banks development team, said that there are no longer plans for townhomes at that location.

Korosec went on to say that the future of that particular site has yet to be determined, but that it is possible it could be used as part of the hotel, but that no decisions have been made.

“That site was originally planned to have six to eight townhomes, which is not really an efficient number to go in and build,” Korosec explained. “Not only was it not efficient, but it also wasn’t going to be a very good environment for townhomes with all the in and out traffic nearby.”

Korosec noted that the elimination of townhomes from the Phase I footprint does not mean that townhomes will not be built elsewhere. In fact, she said that the development team believes there are other sites at The Banks that would be better suited for such housing.

Part of the change can also be explained by the housing bubble that burst around the time construction started at the site.

“The market on condos and townhomes turned south just when we signed the MDA,” Korosec said. “However, homeownership via condos is still a strong possibility at The Banks for future phases should the market demand it.”

The development team opted to forgo building condos at $91 million Phase IA of The Banks, and instead built apartments due to the housing downturn. The decision has proved successful as apartments at The Banks fetch some of the highest prices per square foot in the region and have a waiting list of approximately 60 people.

Since that time the MDA was signed, however, the owner-occupied housing market has shown signs of life throughout the center city where there is currently little supply available. Recent developments, led by 3CDC in Over-the-Rhine, have sold quickly and, in some cases, for more than $300 per square foot.

The Banks development has drawn a significant amount of publicity since its first phase opened in 2011, but work is far from over at the massive riverfront project site. As of now, The Banks is only approximately one-third of the way built out.