Dave Prather and the Cincinnati Park Board have released a new video update on Smale Riverfront Park. This latest update covers a lot of information due to the infusion of millions of new public dollars into the project.
In early March the U.S. Army Corps of Engineers (USACE) announced that they had awarded $4.5 million to Smale Riverfront Park to pay for erosion and flooding control along that portion of the Ohio River.
What it also means is that the Cincinnati Park Board can use other private funding it has received for other components that had been planned for the Heekin/PNC Grow Up Great Adventure Playground but put on hold until additional funding was secured. Those items include a shade canopy, sandbox, enhanced lighting and landscaping, shade trees, granite seat walls, and shade pergola.
Since this additional work can now proceed, project officials have adjusted the overall project schedule so that it can proceed immediately and be completed at the same time as ongoing work, which is slated to open in spring 2015 ahead of Major League Baseball’s All-Star Game to be held at Great American Ball Park.
The City of Cincinnati also approved $8 million in additional funding for the park at the end of last month. That money, officials say, will fund the rest of the next phase of work. City leaders also note that an additional $5 million in city funds will be needed for the project in 2017 to fully complete the park.
The new funding from USACE is the first federal investment in the project in years following a ban on earmark spending that had jeopardized the schedule for completion for the 45-acre central riverfront park.