Great weather seems to always bring great news for construction projects, and this is the case in the latest project update for Cincinnati’s $120 million Smale Riverfront Park.
In the video, project manager Dave Prather points out that the structure enclosing Carol Ann’s Carousel now has its roof decking and framing in place, with the glass wall panels being readied for installation soon. Prather further showed where the elevator shaft has been completed and the large skylight that will form the roof of the building, thus allowing for a flood of natural light inside.
“Keep an eye on this side, it’s really gonna have a transformation” Prather noted. “But right now you can get a sense of how open the structure is.”
Since the last project update, the cascade water features and light fixtures are now in place at the Vine Street Fountain & Steps, which mirror the setup at the already complete Main Street Fountain & Steps. The area is now just awaiting the installation of its granite surface.
One of the more interesting elements of this project update is the excavation work at the river’s edge to make way for the Great Lawn. Now virtually complete, the excavation work as created a beach of sorts going directly into the Ohio River. The completion of this work has also opened up a variety of new views of the Roebling Suspension Bridge that were not previously visible.
Prather then discussed a wall that is now in place along the river bank where the riverwalk will continue from already completed portions of the sprawling park.
“We are now able to connect with the river in a way never had before,” Prather noted proudly.
All components of the current phase of construction work are still anticipated to be completed in late spring or early summer ahead of the 2015 MLB All-Star Game to be held at Great American Ball Park.