The exterior structure is now largely complete for the $86 million Nippert Stadium renovation and expansion project.
According to project manager Bob Marton, the construction team will now largely be focused on interior work, but that the exterior façade will really take shape over the next few weeks.
Similar to other construction projects around the city, the brutally cold and snowy weather lately has slowed down progress. Marton says, however, that they were able to shift some workers to interior projects, and that they will work some extra shifts to make up the lost time.
“We were able to put a lot of workers indoors, but the weather really slowed us down on the outside,” Marton explained in the latest project update. “We need to keep that work rolling as much as we can, because we want to get enclosed by the end of the month.”
He went on to say that the weather caused three to four days of delay. While work will continue to blaze ahead over the coming months in preparation of the University of Cincinnati’s home season football opener on Saturday, September 5 against Alabama A&M.