Categories
News Transportation

Long-Planned $30M Lytle Tunnel Rehabilitation to Begin Next Week

ODOT project officials say that work will begin on the $30 million project that will bring the Lytle Tunnel up to current fire and design standards, while also paving the way for a rebuild of the park above it.

Ohio Department of Transportation officials have announced that work will begin next week on the $30 million rehabilitation of Lytle Tunnel.

Construction crews will begin work on Tuesday, May 26 to add ITS cameras, a fire detection system, upgrade tunnel lighting, repair existing concrete and tiling, upgrade mechanical and ventilation systems, install a new power supply and replace existing underground vaults under the Fourth Street sidewalk.

In addition to this, ODOT crews will move the tunnel’s ventilation system and add new access hatches to several locations so as to not interfere with future plans for Lytle Park.

The work will require Lytle Park itself, and portions of Lytle Street to be closed while construction takes place. Gary Middleton, ODOT District 8 Acting Deputy Director, says that the effort will take approximately two years, with completion coming near the end of 2017.

Over that period of time, the work is expected to cause some headaches for those driving in the immediate area. In particular, project officials are saying that they will go to great lengths to avoid impacts during major events like the All-Star Game, Riverfest and Oktoberfest.

While numerous small disruptions will occur, project officials have noted that the work will force an entire weekend closure of southbound I-71 and the southbound I-71 ramp to Third Street. The southbound I-71 ramp to Third Street will be closed at a later period for 20 consecutive calendar days. The longest closure off all, however, will be when the Second Street ramp to northbound I-71 is closed for 60 consecutive calendar days.

While some scheduling details have yet to be ironed out, Middleton says that a detailed road closure schedule will be released in mid-June.

The road closures will add to those already found all over the center city due to the huge volume of construction taking place that is adding hundreds of residences, hotel rooms, offices and introducing new public transportation and park amenities.

While officials at the City of Cincinnati have not made a specific statement on the matter, the road closures, once finalized, are expected to be posted and updated on RoadmapCincy.com.

The work may also require the closure of the eastern portions of the 2.3-acre park to be closed for up to 10 months.

“This essential project will complete a major rehabilitation of the tunnel and its mechanical and electrical systems, improve safety for drivers and first responders, and ensure future maintenance activities minimize impacts to traveling public and users of the park,” Middleton said.

While the work on Lytle Tunnel, which was originally built in 1970, will be largely unseen, the updates will bring the tunnel into compliance with current fire codes and design standards. It is also presenting a unique opportunity to make improvements to Lytle Park at the same time – an effort that Western & Southern Financial Group has been strongly advocating.

According to ODOT documents, the project is currently on-schedule, but is now estimated to cost approximately $8 million more than what was originally planned.

By Randy A. Simes

Randy is an award-winning urban planner who founded UrbanCincy in May 2007. He grew up on Cincinnati’s west side in Covedale, and graduated from the University of Cincinnati’s nationally acclaimed School of Planning in June 2009. In addition to maintaining ownership and serving as the managing editor for UrbanCincy, Randy has worked professionally as a planning consultant throughout the United States, Korea and the Middle East. After brief stints in Atlanta and Chicago, he currently lives in the Daechi neighborhood of Seoul’s Gangnam district.