VIDEO: Latest Phase of Work at Smale Riverfront Park Virtually Complete

Cincinnati Park officials have celebrated a string of openings at Smale Riverfront Park over the past month. While a few more openings remain, the vast majority of work in the latest major phase of the $120 million park is now essentially complete.

In the latest video update from project manager Dave Prather, he explains what all has taken place and what remains before work slows down considerably. At this point, Prather said, attention will turn to raising funds for the next wave of work, including the boat dock and western reaches of the 45-acre park.

The latest additions to the central riverfront park are more active than what has been developed so far. There are more of the popular family swings overlooking the river, an interactive foot piano, a flying pig playset, water pumps and channels, Carol Ann’s Carousel, and the P&G go Vibrantscape. Where railyards once existed, there are now even movable picnic tables sat atop rail ties.

Two of the larger features of the latest expansion are actually passive spaces. The Great Lawn is now nearly complete and the “beach” is in its early stages of formation. Once complete, visitors will be able to walk all the way down to the water’s edge, although this “beach” will not be made of sand due to the risk of erosion.

Two unique historical features are also part of this latest work. The first is a cornerstone marker in the middle of the Great Lawn that shows where the first addressed building in Cincinnati was situated. The second is a collection of foundation walls that were uncovered during the park’s excavation. These foundations, historians say, remain from 19th century buildings developed along the Ohio River.

This is expected to be the last video update from the Smale Riverfront Park development team for some time. As development at The Banks catches up, the park will soon be able to continue its westward expansion.

Categories
Development News

PHOTOS: Construction Updates From Along the Mighty Ohio River

Both sides of the Ohio River are full of construction right now. In Cincinnati, General Electric’s new Global Operations Center, 300 new apartments, and 60,000 square feet of retail space are under construction at phase two of The Banks. The latest phase of the Smale Riverfront Park, which includes Carol Ann’s Carousel, is also moving along just around the corner.

Then, across the river in Newport, 238 apartments, 8,300 square feet of retail space, and an Aloft hotel are being added as part of the next phase of Newport on the Levee. Prep work is also taking place for the relocation of Kentucky Route 9 and the long-delayed Ovation project.

You can click on any image to enlarge it.

EDITORIAL NOTE: All 13 photos were taken by Travis Estell for UrbanCincy between January 18 and February 15, 2015.

Categories
Arts & Entertainment News

VIDEO: Smale Riverfront Park’s Carousel Taking Shape in Mansfield

Carol Ann’s Carousel is taking shape about three hours north of Cincinnati in Mansfield. It is there where master wood carvers are hand-crafting the $1 million showpiece for Smale Riverfront Park.

Carol Ann’s Carousel is being built by an Ohio company that claims to be world’s largest manufacturer of wooden carousels. Founded in 1986, Carousel Works has built dozens of the rides that are now in operation throughout North America. According to their employees, Cincinnati’s is one of the more unique and interesting projects they have worked on to-date.

“I’ve got to work on some really fun ones so far, but I have to say that the Cincinnati’s carousel is going to be really fantastic,” explained carver Tim Gorka. “I  really think it’s going to be a favorite of most of the people working here.”

The $4.5 million structure that will house the amusement ride is now largely in place, with the glass walls and roofing all in place just west of the Roebling Suspension Bridge along the central riverfront.

Project officials say that the progress is advancing according to plan, and that the 44-character carousel will open to the public on Saturday, May 16.

Categories
Development News

Latest Excavation Work at Smale Riverfront Park Creates Beach Along Ohio River

Great weather seems to always bring great news for construction projects, and this is the case in the latest project update for Cincinnati’s $120 million Smale Riverfront Park.

In the video, project manager Dave Prather points out that the structure enclosing Carol Ann’s Carousel now has its roof decking and framing in place, with the glass wall panels being readied for installation soon. Prather further showed where the elevator shaft has been completed and the large skylight that will form the roof of the building, thus allowing for a flood of natural light inside.

“Keep an eye on this side, it’s really gonna have a transformation” Prather noted. “But right now you can get a sense of how open the structure is.”

Since the last project update, the cascade water features and light fixtures are now in place at the Vine Street Fountain & Steps, which mirror the setup at the already complete Main Street Fountain & Steps. The area is now just awaiting the installation of its granite surface.

One of the more interesting elements of this project update is the excavation work at the river’s edge to make way for the Great Lawn. Now virtually complete, the excavation work as created a beach of sorts going directly into the Ohio River. The completion of this work has also opened up a variety of new views of the Roebling Suspension Bridge that were not previously visible.

Prather then discussed a wall that is now in place along the river bank where the riverwalk will continue from already completed portions of the sprawling park.

“We are now able to connect with the river in a way never had before,” Prather noted proudly.

All components of the current phase of construction work are still anticipated to be completed in late spring or early summer ahead of the 2015 MLB All-Star Game to be held at Great American Ball Park.