VIDEO: New Playground to Open at Smale Riverfront Park in May

Despite all the recent bad weather, work has been progressing on the 45-acre Smale Riverfront Park. The latest phase of construction activity has moved to the west side toward Paul Brown Stadium, and is now becoming visually identifiable.

The next part of the park that will open to the public is the Heekin/PNC Grow Up Great Adventure Playground, which is scheduled to be completed this May.

“The newest feature to be completed is a serpentine wall that’s along the east edge of the playground,” Smale Riverfront Park project manager Dave Prather explained the eight-minute video update. “The way its sculpted entices challenges and encourages folks to do a balance beam walking and being challenged by the narrowness and the way it serpentines its way south toward a toddler-sized slide that is en route and will be installed in the coming months.”

Meanwhile, a series of columns, approximately 75% complete, are now jutting up from the ground at Carol Ann’s Carousel and the Anderson Pavilion.

The glass-enclosed carousel will sit on the upper level of the site that will be flanked by the historic Roebling Suspension Bridge and the Vine Street Fountain & Steps. Cincinnati Park Board officials say that the Vine Street design will mirror that of the currently completed Walnut Street Fountain & Steps.

The Anderson Pavilion will include an event and conference center fronting onto the rebuilt Mehring Way and will sit directly beneath the carousel. Both the carousel and pavilion space are scheduled to open in spring 2015.

Prather goes on in great detail about the various construction activities, taking place now, and lays out what construction work will be taking place in the months ahead.

“There’s going to be a lot happening in the next six weeks or so.”

Categories
Business Development News

First Elements of Cincinnati’s New $120M Central Riverfront Park Coming Online

As mid-rise residential buildings rise from the ground nearby at The Banks, the Cincinnati Riverfront Park (CRP) is making significant progress of its own. Phase 1 of the $120 million, 45-acre park is now just one year away from completion and the first elements of the park are becoming recognizable.

Crews have completed the installation of twenty, 300-foot geothermal wells that will heat and cool several facilities within CRP’s first phase. At the same time construction workers are finishing work on the realigned Mehring Way which will free up direct riverfront space, create a more user-friendly street for all modes of transportation, incorporate space for the Ohio River Trail, and maintain the roadway’s necessary specifications for hazardous materials transportation.

In this fall 2010 update, Project Manager Dave Prather also discusses how meticulous the project team has been in their selection of materials including the granite which will be prominently used throughout this first phase.

The Head House that connects the underground parking garage to the park is the first feature of the Cincinnati Riverfront Park to be completed.  The next elements to come online will be the Schmidlapp Stage & Event Lawn in May 2011 with the Moerlein Lager House following shortly thereafter. Project officials expect the Walnut Street Fountain & Steps and Bike, Mobility & Visitors Center in late summer 2011.  The remaining features of Phase 1 will be completed next fall.