PHOTOS: Construction Activities for $133M Streetcar Project Move Southward

Since the dust-up in December, construction work on the $133 million first phase of the Cincinnati Streetcar has been proceeding as planned.

Those living, working or visiting Over-the-Rhine, can now see significant visual progress throughout much of the neighborhood. Meanwhile, utility relocation and upgrade work continues near the southern terminus of the initial system; and now track work is beginning to approach as rails are installed along Central Parkway.

Due to the congestion and centuries old utility systems, work in the Central Business District is expected to be messy and lengthy. In order to minimize disruptions, city officials say that they are working as much as possible at night and on weekends.

Vertical construction continues at the system’s northern terminus where the Maintenance & Operations Facility is being built; and officials say that work is now beginning on one of the first power substations at Court Street and Walnut Street.

Restoration of the Central Parkway median is currently taking place following a surge of construction activity along this stretch of the route, which, coincidentally, is located directly above the Race Street Station for the never-completed Cincinnati Subway.

Rail installation will continue to take place throughout Over-the-Rhine in the coming weeks, and gradually work its way south. Meanwhile, expect the heavy lifting that is the modernization and relocation of utilities to continue.

Due to encouraging progress, some project officials believe there is the possibility the system could open several months ahead of schedule sometime in the summer of 2016.

It was also learned this week that the Southwest Ohio Regional Transit Authority (SORTA), the agency who will eventually operate the system, will deposit $268,278 of a remaining 1996 grant from the Federal Transit Administration into the Cincinnati Streetcar’s unallocated contingency fund. That fund, meant to cover unanticipated costs, started out at $4.7 million. Since the start of the project officials have used nearly $900,000 of those funds.

EDITORIAL NOTE: The following 22 photographs were taken by Jake Mecklenborg on Tuesday, May 20, 2014. Those interested in learning more about Cincinnati’s transit history should read his book – Cincinnati’s Incomplete Subway: The Complete History.

Categories
Development News Transportation

VIDEO: UC Students, Transportation Experts Pitch Their Ideas for Wasson Corridor

As part of UrbanCincy‘s ongoing partnership with the University of Cincinnati’s Community Design Center, we gathered interested members of the public at the Niehoff Studio in Corryville on April 17 to view the work of students studying the Wasson Corridor.

As with previous events we have hosted at the Niehoff Studio, a capacity crowd attended to not only view the student work, but also participate in a panel discussion with regional experts on the topic. At this event, UrbanCincy‘s Jake Mecklenborg moderated the discussion.

The topic of discussion and the proposals put forth by the interdisciplinary students carried even greater weight as the City of Cincinnati allocated $1.9 million for a variety of bike projects, including $200,000 for the Wasson Way Trail. The City has also recently made an offer to purchase the Wasson Corridor for $2 million from Norfolk Southern who abandoned the rail line years ago.

While the Wasson Way Trail envisions a recreational bicycle and pedestrian trail running along the Wasson Corridor, many now view it as a component of a multi-modal transportation corridor that includes a long-planned light rail line.

Mayor John Cranley’s (D) administration appears to be focused on investing in recreational bike/ped trails, which is good, but the development of the Wasson Corridor should include both the proposed recreational trail and room for light rail tracks.

Fortunately, what was once viewed as a project that pitted light rail advocates against biking advocates has changed drastically since UrbanCincy‘s controversial editorial on the matter in 2012. There now appears to be broad consensus from both sides that the corridor should be developed in a comprehensive, multi-modal fashion.

Categories
Development News Transportation

UrbanCincy, Niehoff Studio to Host Regional Discussion on Wasson Corridor

In May 2013, UrbanCincy partnered with the Niehoff Urban Studio to produce an event that highlighted the final work of engineering and urban planning students studying bus rapid transit and bikeways throughout the region. We then showcased their work and engaged the capacity crowd with a panel discussion between some of the region’s foremost experts on the subjects.

One of the hot topics at that event was the Wasson Corridor, which runs through the heart of Cincinnati’s eastern neighborhoods.

The Future of the Wasson Way Bike Trail and Light Rail Corridor

The corridor has long been in regional transit plans as the location for a light rail line, but recent advocacy efforts have been working to convert the abandoned freight rail right-of-way into a recreational trail for bicyclists and pedestrians.

Following UrbanCincy’s controversial editorial opposing the corridor’s conversion into a bike/ped trail, the conversation has shifted to one focused on creating a multi-modal corridor that accommodates the long-planned light rail and the newly envisioned recreational trail.

The next stage of that dialogue will occur this Thursday back at the Niehoff’s Community Design Center in Corryville.

Over the past semester, interdisciplinary students from the University of Cincinnati have been studying the Wasson Corridor and will be presenting their work at this event.

Following the open house where guests can view the final projects, UrbanCincy will then host a panel discussion with Michael Moore, Director of Cincinnati’s Department of Transportation & Engineering (DOTE); Eric Oberg, Manager of the Midwest Rails to Trails Conservancy; Mel McVay, Senior Planner at Cincinnati DOTE; Nern Ostendorf, Executive Director of Queen City Bike. The discussion will be moderated by UrbanCincy’s Jake Mecklenborg.

The event is free and open to the public. The open house portion of the evening will take place from 5pm to 6pm, and the panel discussion will follow immediately at 6pm and go until about 7:30pm.

Light food and refreshments will be provided and a cash bar will be available during the open house. The Niehoff’s Community Design Center can be accessed directly off of Short Vine at the southeast corner of Daniels and Vine Street.

Categories
Business News Opinion

Celebrating a Great 2013 While Looking Ahead to Our Eighth Year

Another year has come and gone, and I wanted to take this opportunity to recap some of the highlights from 2013 while also looking to the future.

Our readership remained constant in 2013, with accelerated growth in Q4. We expect readership levels to hold at those increased Q4 rates throughout 2014, while recording some additional modest growth. Perhaps not surprisingly, our biggest month was December when the streetcar battle culminated.

More people listened to The UrbanCincy Podcast – now entering its second year – than ever before. The most popular episode last year was our yearly recap at the start of 2013 followed by our interviews with David Ginsburg from DCI and Kevin Wright from the Walnut Hills Redevelopment Foundation. Overall we had more than 109,000 downloads of The UrbanCincy Podcast in 2013 and averaged nearly 7,000 downloads per episode.

UrbanCincy Readership Trends

Staff Changes
Our staff also grew and changed a bit last year. As many of you know, I am temporarily on assignment in Seoul and John Yung has become our local area manager. Travis Estell continues to serve as our technologist and podcast manager, while Jake Mecklenborg continues to perform in-depth reporting on transportation issues and produce much of our photography.

We added two new staff writers in 2013 as well – Caitlin Behle and Paige Mallot. They will be covering a variety of topics, but will help expand UrbanCincy’s coverage of arts and entertainment. A third new staff writer – Jacob Fessler – has contributed some already, but will begin his work covering the region’s urban economics and industry in 2014. We also began working with the talented Nate Wessel and Andrew Stahlke to produce custom maps and videos that complement our stories.

We have an incredible team and none of this would be possible without their dedication and hard work. If you see them out and about, you should treat them to a cup coffee or a glass of beer.

Partnerships
In February we entered into an agreement with the Niehoff Urban Studio to produce events that highlight the interdisciplinary work and research performed by students at the University of Cincinnati. That led to our Metropolis & Mobility event in April and our Urbanist Candidates Forum just prior to November’s election.

We have continued to bolster our exclusive partnership with the Business Courier as well. In addition to our readers getting discounted access to a digital premium subscription, we are also sharing more of our content with them so that our reporting on the city reaches an even larger audience in both print and on the web.

In 2014 we hope to enter into additional partnerships that will help get our content to even more people throughout the region and engage more people with the city.

Events
After starting URBANexchange in 2012, we have continued to host the monthly social event at the Moerlein Lager House. Now typically on the first Thursdays of each month, the events consistently draw a diverse collection of 20 to 40 people interested in urbanism. Many of these people are either new to Cincinnati or are looking to get more involved, and I am happy to say that these events are helping grow Cincinnati’s urbanist community.

In 2014 we will continue hosting the events and continue to engage you with area policy makers and influencers, and work to gather your thoughts and ideas about important policy issues. Plus, we hope to keep giving away unique prizes. Hopefully you can join us at our first URBANexchange of the New Year on Thursday, January 9 from 5:30pm to 8:30pm in the Moerlein Lager House’s biergarten.

Urbanist Candidates Forum

Content
One of the things UrbanCincy has always tried to do is connect area residents and visitors with the things happening in the city. This is still true today, but we are now fortunate to have a national audience. So while our focus is still on providing local coverage of public policy, urban design, transportation, arts and culture, we are now also connecting people from around the country with what is taking place here.

In 2013 we published 145 original stories, published 10 perspectives from readers in guest editorials, shared 103 of our insights about what we thought was interesting news from elsewhere in our Up To Speed posts, and produced 16 podcasts. Our ten most read stories in 2013 were:

  1. December 2, 2013: The Day Chaos Ruled City Hall: http://urbn.cc/p3ri
  2. Proposed 210-Unit Apartment Development Would Demolish Historic Christy’s & Lenhardt’s: http://urbn.cc/p2xy
  3. Final Designs Revealed for $125M Dunnhumby Centre Tower: http://urbn.cc/p3i3
  4. Pogue’s Garage to Make Way for 30-Story Residential Tower, Grocery Store: http://urbn.cc/p2yx
  5. EDITORIAL: Localizing Operating Costs for Streetcar Sets Dangerous Precedent: http://urbn.cc/p3sl
  6. GUEST EDITORIAL: Get Over It, Then Get Ready: http://urbn.cc/p3pk
  7. GUEST EDITORIAL: Horseshoe Casino Fails to Deliver on Urban Design: http://urbn.cc/p2zb
  8. IMAGE: Cincinnati to Grow Taller in the Coming Years: http://urbn.cc/p37p
  9. PHOTOS: Historic Glencoe-Auburn Place Row Houses Are Being Demolished: http://urbn.cc/p31l
  10. The Plot Continues to Thicken for Cincinnati’s $133M Streetcar Project: http://urbn.cc/p3s7

We also had two other stories that garnered a significant amount of interest by the way of comments, but didn’t crack the top ten for readership. The story readers commented on the most in 2013 was Paige’s opinion piece about Diner En Blanc held at Washington Park (104), and the second most comments (89) were left on our editorial calling for the consolidation of local governments in Hamilton County.

Our team also traveled to help bring additional perspective from other cities throughout the country and abroad. In 2013 John brought you stories from Europe and Portland; Jake traveled to Nashville; and I filed reports from Kansas City, Los Angeles, Salt Lake City, Seoul and Chicago. We will continue to use our travel to bring even more perspective into the issues we cover in Cincinnati. In 2014 we have already planned reports from Denver, Houston, Dallas, Minneapolis, Bangkok, Seattle, Hong Kong, Seoul, Nashville and Atlanta.

In 2014 you will also see us advocate more for specific projects and policy recommendations, based on our research and collaborations. In the past we have advocated for changing the city’s parking requirements, overhauling the city’s zoning code, and how to use the Riverfront Transit Center. In the coming weeks you will hear even more specific solutions from our team about how to address various problems and opportunities in our city today.

It has been nearly seven years since UrbanCincy started, and we are thrilled it is has become one of the largest independent sources for news in the region, and one of the most well-read websites focused on urbanism in the country.

We have some big plans for the year ahead and we hope that you will stick along for the ride. And while you’re at it, why don’t you bring a few friends. Thanks for all of your support.