Categories
News Transportation

All Aboard Ohio Celebrates Recent Successes, Future Plans at Recent Meeting

Last Tuesday, All Aboard Ohio held their Spring meeting at the newly-opened Taft Ale House in Over-the-Rhine.

President of the Southwest chapter, Derek Bauman, ran the meeting, which not only included discussion of advocacy for interstate passenger rail in Cincinnati, but also of the ongoing construction of the Cincinnati Streetcar.

Several community leaders and representatives were present, including Streetcar Project Manager John Deatrick, Metro’s Rail Operations Manager Paul Grether from Metro, the chief of staff for Councilman Kevin Flynn, a representative from the Cincinnati Preservation Society, the president of Queen City Bike, and even Cincinnati Union Terminal’s Amtrak station manager.

To begin the meeting, Deatrick and Grether talked about the construction of the streetcar system, which can be seen directly outside of Taft’s Ale House, and the future operation of it. Deatrick informed the crowd that almost 70% of the construction is complete, which is ahead of schedule, and the city expects the first streetcar delivery by September.

When asked to address the ongoing discussion about the next phase to Uptown, Deatrick declined to comment.

Grether then explained how his organization acts as the conduit for federal funds to the streetcar and will be the future operator of the system. He also discussed Metro’s plans to schedule the streetcar in a manner that complements and fully integrates with Metro’s bus operations, and those of TANK.

Another key point that Grether mentioned is that the technology is in place to be able to give streetcars signal priority, should leaders at City Hall decide that is desirable. Such a move would quite significantly improve travel times and performance.

As the conversation moved on, Bauman spoke about the group’s efforts to establish daily passenger rail service between Cincinnati and Chicago. Not having daily rail service to Chicago damages business competitiveness for the city, Baumann said, considering that Milwaukee, St. Louis, Detroit and Indianapolis already currently boast such service.

The effort has received renewed interest as of late due to the debate surrounding the future of the Hoosier State line, which connects Chicago to Indianapolis. Project proponents scored a big win recently when funding was picked up by the State of Indiana to continue its service. Those efforts even attracted the attention of Senator Joe Donnelly (D-IN) in a letter he penned to the Federal Railroad Administration about the possibility of future extensions of the line.

Since assuming the presidency of the local chapter, Bauman has made a variety of changes to allow for greater participation and engagement. Meetings are no longer confined to members, for example, and they have begun reaching out to the business community and area universities.

Bauman said that he hopes this approach will help make daily passenger rail service a reality for the Cincinnati region at some point in the near future.

Those that are interested in supporting the efforts of All Aboard Ohio can do so by making a tax-deductible donation to the organization on Tuesday, May 12. On this day the Columbus Foundation will make matching donations to a collection of non-profits throughout the state, including All Aboard Ohio. You can make secure donations to the group on their website.

Categories
News Transportation

System Designs Unveiled, Operating Agreement Reached for Cincinnati Streetcar

Officials with the City of Cincinnati and Southwest Ohio Regional Transit Authority (SORTA) made several major announcements last week pertaining to the rollout of the Cincinnati Streetcar system.

While the design of the rolling stock and the system’s color scheme were revealed more than a year ago, the official branding for the new mode of transit for the Cincinnati region had not. SORTA officials say that the branding will be utilized all throughout the system including its fare cards, ticketing machines, uniforms, wayfinding, brochures, website and social media, and, of course, the trains and their stations.

The branding scheme was put together by Kolar Design, whose offices are located in the Eighth Street Design District just two blocks from the nearest streetcar stop, after competing with more than 100 other firms interested in the opportunity to developing the design scheme.

Project officials say that the $25,000 cost for the branding effort was paid for through Federal funds.

Founders Club Card Sales
At the same time, SORTA and City officials announced the availability of 1,500 Founders Club Cards. The sale of the cards, officials said, would help raise some initial funds to be used to help offset initial operating expenses.

Project officials have informed UrbanCincy that approximately half of the 1,500 cards were sold within the first 24 hours of going on sale; and that more than 1,000 had been sold by Friday. A limited number of Founders Club Cards are still available for purchase at the Second Floor Cashier’s Office at City Hall, Metro’s sales office in the Mercantile Arcade across from Government Square, and online at Metro’s website.

There are three card options available. The first goes for $25 and allows for unlimited rides for the first 15 days of service, which is currently pegged for 2016. The second and third options go for $50 and $100, and allow for unlimited rides for the first 30 and 60 days, respectively.

The commemorative metal cards and matching metal cases were seen by some as one of the first ways for Cincinnati Streetcar supporters to show their support. Having experienced strong sales thus far, it seems as Metro’s strategy may prove to be a success.

“This is one of the first tangible opportunities streetcar enthusiasts can show their support,” said City Councilwoman Amy Murray (R), Transportation Committee Chair. “This is a great idea that Metro has developed to generate excitement. I think many will appreciate the privilege of being a Founding Club Member with this commemorative card.”

Operating Agreement Finalized
Perhaps lost amid the other news was the signing of an official operating agreement. Under the current structure, the City of Cincinnati is building the system, and is its owner, but will contract out its operations to SORTA.

The Cincinnati Streetcar Operating & Maintenance Agreement first came out of Murray’s Transportation Committee and was approved 7-2 by City Council in early November. It calls for expanded on-street parking enforcement in Downtown and Over-the-Rhine until 9pm, an increase in parking rates in those two neighborhoods, and a set streetcar fare of $1 for two hours.

The agreement also utilizes an innovative technique that would lower property tax abatements 7.5%. This is an important component of the agreement as it addresses a longstanding call from opponents for those benefiting from real estate valuation increases to cover more of the costs of modern streetcar system. It also eliminates the need to utilize the Haile Foundation’s $9 million pledge, and would instead only tap into those funds in a worst-case scenario.

Project officials estimate that the system will cost approximately $3.8 to $4.2 million annually to operate, and that those costs would be covered by $1.5 million in additional on-street parking revenue in Downtown and Over-the-Rhine, $1.3 million from fares and advertising, and an estimated $2 million annually from the tax abatement reductions.

“This is the most innovative plan I’ve seen in the United States,” stated John Schneider, noted transit advocate and real estate developer, at the time of City Council’s approval in November.

The SORTA Board approved the agreement last week and touted the benefits of having operations of the Cincinnati Streetcar be handled through Metro, which also runs the region’s largest bus service.

In addition to the critical financing elements of the agreement, it also delineates various responsibilities once service goes into effect. To that end, the City of Cincinnati will be in charge of maintaining traffic signals, clearing blockages from the streetcar path, cooperation on utility interfaces, safety and security; while SORTA will be responsible for operating the system, maintaining vehicles and facilities, fare collection provision and maintenance, marketing and advertising sales.

Construction on the $148 million first phase of the Cincinnati Streetcar continues to progress, with most track work in Over-the-Rhine now complete and track work now progressing through the Central Business District. Current time frames call for operations to begin in September 2016.

Categories
Business Development News Transportation

PHOTOS: Construction Activities for $133M Streetcar Project Move Southward

Since the dust-up in December, construction work on the $133 million first phase of the Cincinnati Streetcar has been proceeding as planned.

Those living, working or visiting Over-the-Rhine, can now see significant visual progress throughout much of the neighborhood. Meanwhile, utility relocation and upgrade work continues near the southern terminus of the initial system; and now track work is beginning to approach as rails are installed along Central Parkway.

Due to the congestion and centuries old utility systems, work in the Central Business District is expected to be messy and lengthy. In order to minimize disruptions, city officials say that they are working as much as possible at night and on weekends.

Vertical construction continues at the system’s northern terminus where the Maintenance & Operations Facility is being built; and officials say that work is now beginning on one of the first power substations at Court Street and Walnut Street.

Restoration of the Central Parkway median is currently taking place following a surge of construction activity along this stretch of the route, which, coincidentally, is located directly above the Race Street Station for the never-completed Cincinnati Subway.

Rail installation will continue to take place throughout Over-the-Rhine in the coming weeks, and gradually work its way south. Meanwhile, expect the heavy lifting that is the modernization and relocation of utilities to continue.

Due to encouraging progress, some project officials believe there is the possibility the system could open several months ahead of schedule sometime in the summer of 2016.

It was also learned this week that the Southwest Ohio Regional Transit Authority (SORTA), the agency who will eventually operate the system, will deposit $268,278 of a remaining 1996 grant from the Federal Transit Administration into the Cincinnati Streetcar’s unallocated contingency fund. That fund, meant to cover unanticipated costs, started out at $4.7 million. Since the start of the project officials have used nearly $900,000 of those funds.

EDITORIAL NOTE: The following 22 photographs were taken by Jake Mecklenborg on Tuesday, May 20, 2014. Those interested in learning more about Cincinnati’s transit history should read his book – Cincinnati’s Incomplete Subway: The Complete History.

Categories
Business Development News Politics Transportation

Project Executive Estimates Cost to Cancel Streetcar Would Far Exceed $100M

The project executive for the Cincinnati Streetcar project, John Deatrick, gave a presentation to Cincinnati City Council’s Budget & Finance Committee today to outline the anticipated costs, time frame risks associated with cancelling or temporarily stopping work on the $133 million project.

Deatrick emphasized that at this point approximately $32 million has or will be spent prior to December 1. In addition to that, he explained exactly why the city would forfeit approximately $45 million in Federal funds, and be subject to local payment of any funds committed that would have otherwise been paid by those Federal funds. In addition to that, Deatrick and the project team estimate that it would cost $31-48 million to close-out the project.

Streetcar Cancellation and Close-Out Costs


What it means is that the professionals involved with overseeing the project believe the costs to cancel will be between $108 million and $125 million, not including any of the highly anticipated litigation costs.

The presentation also included a breakdown of more intangible numbers like the damage to the reputation the city has with the Federal government, and the future inability to receive Federal funding for any transportation projects as a result.

Cincinnati’s Budget Director, Lea Erickson, then explained how those costs would be paid and that the cancellation of the project would also result in the loss of any realized property and economic gains anticipated due to the streetcar, as outlined by an economic feasibility report done by HDR Economics. That total of lost tax revenue for the City of Cincinnati and Cincinnati Public Schools, she estimates, would $237 million in today’s dollars – or $594 million over the course of the next 35 years.

The 39-page presentation is packed with detailed breakouts and explanations for these figures. It also explains the relationship of the various contractors involved in the project.

Categories
Development News Politics Transportation

Hidden Assets of Fort Washington Way Saving Taxpayers Millions of Dollars

Each Wednesday in July, UrbanCincy is highlighting Fort Washington Way (FWW), the I-71/US-50 trench bisecting the Cincinnati riverfront from its downtown. Part-one of the series discussed what the area looked like prior to reconstruction a decade ago, and how that reconstruction made way for the development along Cincinnati’s central riverfront. This week’s piece will discuss some of the unseen assets included in the project that continue to benefit Cincinnatians in a variety of ways today, and will continue to do so well into the future.

Those who enjoy spending their summer evenings at Great American Ball Park to watch our first-place Reds, or our defending AFC North Champion Bengals, have probably seen the stairway entrances to the Riverfront Transit Center. Below Second Street, along the southern portion of FWW, lies an underground multi-modal transit facility. Demonstrating a tremendous amount of foresight, engineers constructed a transit center reportedly capable of moving 500 buses into and out of the heart of downtown in an hour.  This is in addition to Second Street which is designed to also accommodate light rail and streetcars at street level while the underground portion is capable of accommodating light rail, commuter rail, and buses.  And all of this was designed with future transit connections to Northern Kentucky via the Taylor Southgate Bridge, and Cincinnati’s eastern and western suburbs via Riverside Drive and Longworth Hall respectively.

As The Banks development continues its exciting march toward completion, its visitors along with those frequenting Great American Ball Park, the National Underground Railroad Freedom Center, and Paul Brown Stadium will use the anticipatory infrastructure available at the transit facility that could eventually be home to trains serving downtown on a regional light rail network – an inclusion that will eventually save taxpayers millions of dollars once light rail begins to serve Cincinnati central riverfront.

But the Riverfront Transit Center is not the only instance of transportation foresight included with the FWW redesign ten years ago. The roadways that span FWW at Main and Walnut streets were both built to withstand the weight or rail transportation. Furthermore, the sidewalks on each of the roadways connecting Second and Third streets over FWW are some of the widest in the city. Knowing the untapped potential of the area that would later become The Banks development, engineers and city officials determined it prudent to build the spans to support pedestrian, vehicular, bus and rail transportation. Now, as the city builds the Cincinnati Streetcar, it can easily and seamlessly connect the central riverfront to the rest of downtown and beyond because the engineers planned for it a full ten years ago.

Another problem along Cincinnati’s central riverfront was the presence of combined sewer overflows (CSOs). The CSOs are the result of an outdated sewer and water pipe system that becomes overloaded during heavy rainfall events. The result is the combination of solid waste and water runoff into our natural waterways like the Ohio River and its tributaries. Due to the health and ecological concerns, the city and county are under a decree to fix the problem over the next decade or so.

Ten years ago, during the reconstruction of FWW, engineers knew that the problem needed to be addressed eventually, so they built storage tunnels along the trench below Third Street. These pipes act as de facto storage tanks when it rains, allowing runoff and raw sewage to stay in the pipes until it can be treated. From this foresight, the number of raw sewage spills in the immediate area has decreased from about 150 per year to around four or five – an achievement determined by ORSANCO to have provided “measurable water quality improvements to the Ohio River.”

Had the engineers not thought to include the transit center below Second Street, installed wide sidewalks for pedestrians, included the capability to safely transport a streetcar, and built water pipes that can withstand the rain, current and future taxpayers would be burdened with the cost of redoing something we constructed a mere decade ago. Building these features before the need arose ensured that the area is not in a constant state of construction. Furthermore, it allows development to proceed more quickly and without additional unnecessary costs.

Ignoring long-term needs is a foolish, dangerous, and potentially expensive way to run a city. While some city leaders of yesterday and today do indeed deserve criticism for a lack of long-term planning, we ought to give credit where credit is due. And the reconstruction of Fort Washington Way is one of those instances. The decisions made by city leaders over a decade ago have saved taxpayers tens of millions of dollars.

Next Wednesday’s segment will discuss how a project involving so many different interested parties could even be accomplished. In the final article, we will provide ideas for the future of the area, and seek feedback from our readers on what the city can do to make the area more inviting.